What is the implementation timeline for SIG Cohort 4?

The implementation timeline is as follows:
  • Year 1: August 1, 2017–July 31, 2018 (Funding during this year may be used for planning and pre-implementation activities)
  • Year 2: August 1, 2018–July 31, 2019 (Full implementation must occur)
  • Year 3: August 1, 2019–July 31, 2020 (Full implementation must occur)
  • Year 4: August 1, 2020–July 31, 2021 (Full implementation must occur)
  • Year 5: August 1, 2021–July 31, 2022 (Funding during this year must be used to implement the sustainability plan)

Last Updated: 12/9/2016